Power Stations
Completed
Abu Qir Thermal Power Plant Units 6 & 7 (2x650 MW Gas/Oil Fired Units)
About the Project
Project Name: Abu Qir Thermal Power Plant Units 6&7 “2X650MW Gas/Oil Fired Units” (Contract no. 119)
Project Total Value: EGP 452.272.540 + Euro 6.363.656 (Total EGP 50 million)
Project Duration: 1070 days ( = 2 years and 11 months)
Starting Date: 6/9/2009
Completion Date: 10/8/2012
Owner: West Delta Electricity Production Company (WDEPC)
WDEPC’s Consultant: Power Generation Engineering and Services Company (PGESCo)
The Project Site: Al-Tar7 area - 20 km East Alexandria city.
Scope of Work:
1. Channel diversion
2. Intake building
3. Discharge building
4. Pipe lines
5. Marine works
Key Features
Distinctive Architectural Design
Modern design meeting the highest standards
Professional Project Management
Integrated coordination among all stakeholders
High Safety Standards
Full commitment to safety regulations
Exceptional Quality
Execution with the highest quality standards
Start Date
2012